Procurement Case Note (ROI) : Irish Courts Affirm Strict Approach to Limitation Periods
LOC8 Code v Department of the Environment, Climate and Communications and Others
April 03, 2024
Procurement Case Note (ROI) : Irish Courts Affirm Strict Approach to Limitation PeriodsLOC8 Code v Department of the Environment, Climate and Communications and OthersApril 03, 2024 IntroductionA recent judgment of the Irish High Court (Barrett J) has affirmed the strict approach of the Irish Courts to the application of the statutory limitation period to the initiation of public procurement challenges . In 84-page judgment (which for the most part reproduces extensive aspects of the affidavit evidence) the Court found that proceedings brought in relation to pre-qualification requirements some eleven years after those requirements were first published were “very considerably” out of time. BackgroundThe case concerned a tender process conducted by the Department of the Environment, Climate and Communications (the “Department”) in 2011 which led to the award of a contract to develop and implement the national postcode system, Eircode. Following the commencement of the competition in January 2011, Loc8 Code Limited (the “plaintiff”) had queried a pre-qualification rule requiring candidates to meet a minimum turnover requirement of at least €40 million. At the time, the Department maintained that the requirement was reasonable in light of the value of the contract over its proposed 10-15 year term. The Department also reminded candidates that it was open to them to join together for the purposes of satisfying the turnover requirement and participating in the competition. The plaintiff did not accept the Department’s rationale for the turnover requirement. This culminated in its lawyers writing to the Department in February 2011 to request that the competition be abandoned on the basis that the turnover requirement prevented the plaintiff from bidding. The Department responded in April 2011 re-iterating its position and advising that the tender process would proceed. Ultimately, the plaintiff did not tender on its own or as part of a consortium. The procurement went ahead and the contract was awarded to Capita in December 2013.
The plaintiff’s claim and the Court’s decision
On 2 September 2022 (more than 11 years after the procurement process commenced and following various earlier interactions between the plaintiff and the Department in relation to that process), the Plaintiff issued proceedings against the Department, Capita (the successful tenderer) and An Post (the Irish state postal service) challenging the procedure and the contract award and seeking various reliefs. In response, each of the three defendants sought inter alia an order dismissing and/or striking out the proceedings on the basis that they were out of time.
CommentThis appears have been a straightforward decision for the Court, particularly once it came to the view that the various claims advanced amounted effectively to a procurement challenge. It should serve as a reminder, if one were needed, of the strict application of the 30-day time limit in public procurement challenges. This has been endorsed by the Irish Courts on various occasions. It would appear that the plaintiff made no application to the Court to exercise a discretion and waive the applicable time limit, however even if it had the Court considered that this would have been “doomed to fail”. It is possible that the Irish Courts could adopt a more lenient approach to limitation periods in cases where a procurement challenge is commenced after contract award (the fact that a successful plaintiff would not benefit from the automatic suspension of the contract award process is potentially a relevant consideration). However, on this occasion it was simply not to be for Loc8 given in the inordinate delay in bringing the claim. Latest Insights
Latest News
Latest Events
legal updates October 23, 2026 CRU Decision on MPID 345: Fault Ride Through, Demand Caps and a 27 October ... guides and reports October 23, 2026 EU: Empowering Consumers for the Green Transition Directive legal updates October 21, 2026 Navigating energy storage globally legal updates October 21, 2026 Construction Projects in the GCC firm news October 20, 2026 Eversheds Sutherland expands global disputes platform client news October 14, 2026 Eversheds Sutherland advises on the acquisition of The Lake Como EDITION client news October 13, 2026 Eversheds Sutherland advises Clara Trustee on trio of UK superfund transact... client news October 13, 2026 Eversheds Sutherland advises RWE on sale of stake in Five Estuaries Offshor... hybrid Europe Action Week 2026 Europe Action Week returns this November with a dynamic mix of events designed to help you navigate what’s next. virtual French employment law training November 03, 2026 2pm - 5pm (GMT) Virtual virtual Dutch employment law training November 10, 2026 2.00pm - 5.00pm (GMT) Virtual virtual Strategic absence management November 11, 2026 9.30am - 12.30pm (GMT) Virtual |