CRU Decision on MPID 345: Fault Ride Through, Demand Caps and a 27 October Deadline
October 23, 2026
CRU Decision on MPID 345: Fault Ride Through, Demand Caps and a 27 October DeadlineOctober 23, 2026 Key Takeaways
On 22 September 2026 the Commission for Regulation of Utilities (“CRU”) published its decision (CRU2026145) approving Grid Code Modification MPID 345: Fault Ride Through, Rate of Change of Frequency and Post Fault Active Power Recovery for Demand Facilities (the “Decision”). Background: The FRT ProblemFaults on the transmission system are common and are usually isolated very quickly, with voltage recovering to its normal range within around 100 milliseconds. Most grid users ride through them but data centres generally do not. To protect their IT systems they cut their grid import and switch to back-up supply, even when the fault is far away. They can then take some time to return to normal demand. When many sites react this way at the same time, the sudden drop in demand unbalances the system and causes frequency deviations across the island. To manage this risk, EirGrid and SONI have set a 900 MW Load Rejection Limit. This is the largest sudden loss of large energy user and interconnector demand that the all-island system can securely accommodate and it equates to around 1,000 MW of data centre demand. What MPID 345 RequiresMPID 345 adds three technical requirements for every existing and future transmission-connected Demand Facility:
Compliance is measured at the point of connection based on the facility’s aggregate response rather than individual loads or equipment. Behind-the-meter technology such as a co-located Battery Energy Storage System (BESS) can therefore form part of a compliance solution, subject to EirGrid’s assessment. The CRU rejected requests for a longer or staged recovery period for existing facilities and accepted the view of EirGrid and TNEI Ireland (“TNEI”), which carried out an independent technical review for the CRU, that 500 milliseconds is necessary. The Compliance and Derogation FrameworkThe CRU accepts that most existing transmission-connected Demand Facilities cannot comply immediately. EirGrid’s framework provides a route to compliance over time and treats data centres and other facilities differently to reflect their different behaviour during past fault events. There are three derogation routes:
How DUTs work. A DUT caps the monthly average demand that a data centre may draw for its non-compliant load. Each site's DUT is its highest monthly average demand in 2025, plus a pro-rata share of any remaining headroom that the system can securely accommodate. Peaks of up to 10% above the DUT are permitted without prior approval, provided the monthly average stays within the cap; larger peaks need EirGrid's prior written approval. Exceeding the monthly average, or the DUT plus 10% threshold without approval (even accidentally), is a breach of the derogation conditions and therefore of the Grid Code. DUTs will be calculated and monitored using metering data rather than SCADA data, which the CRU has confirmed will change DUT estimates for all customers. Key Changes from the ConsultationThe final Decision largely follows TNEI’s recommendations and departs from the original proposals in several ways:
Future ConsiderationsEirGrid must report to the CRU quarterly from the end of December 2026 on its roadmap to remove the operational constraints used to manage FRT risk, the cost of those measures, updated modelling and progress on compliance. It must also set a timeframe for that roadmap within five weeks of the Decision. An FRT Implementation Working Group will support demand customers working towards compliance and is expected to meet first in November 2026. An equivalent modification has been approved in Northern Ireland by the Utility Regulator and ESB Networks intends to propose a Distribution Code modification for distribution-connected facilities. Next Steps for Data CentresMPID 345 takes effect on 27 October 2026. Facilities that cannot yet demonstrate compliance should:
ConclusionMPID 345 turns fault ride through from emerging good practice into a binding Grid Code obligation for large energy users. For data centres in particular, the DUT means that any delay in achieving compliance will translate directly into constrained growth. Early engagement with EirGrid, a realistic compliance plan and a clear view of the commercial impact of any DUT will be essential. For further information please see: LINK Latest Insights
Latest News
Latest Events
legal updates October 23, 2026 CRU Decision on MPID 345: Fault Ride Through, Demand Caps and a 27 October ... guides and reports October 23, 2026 EU: Empowering Consumers for the Green Transition Directive legal updates October 21, 2026 Navigating energy storage globally legal updates October 21, 2026 Construction Projects in the GCC firm news October 20, 2026 Eversheds Sutherland expands global disputes platform client news October 14, 2026 Eversheds Sutherland advises on the acquisition of The Lake Como EDITION client news October 13, 2026 Eversheds Sutherland advises Clara Trustee on trio of UK superfund transact... client news October 13, 2026 Eversheds Sutherland advises RWE on sale of stake in Five Estuaries Offshor... hybrid Europe Action Week 2026 Europe Action Week returns this November with a dynamic mix of events designed to help you navigate what’s next. virtual French employment law training November 03, 2026 2pm - 5pm (GMT) Virtual virtual Dutch employment law training November 10, 2026 2.00pm - 5.00pm (GMT) Virtual virtual Strategic absence management November 11, 2026 9.30am - 12.30pm (GMT) Virtual |